Pool Construction
Before
Day 1
The digging!
Day 2
Framing of the pool....
Day 3
Digging the big Hole!!!
Day 4
Framing the inside wall of pool...
Day 5
more framing for gunite......
Day 6
Spaying in Gunite!!!
Day7
Smoothing patio surface.....
Day 10
installing water pipes....
Day 13
Beginning tile work!!!
Day 16
Tiles all layed out!
Day 17
Framing for concrete patio!!!
Day 18
installing metal footers for extra support!
Day 19
framing for Cement deck!
Day 20
Pouring cement deck!
Day 22
Painting Deck.................
Day 24
Cleaning out the sludge on the inside to prepare
for the inside finish....
Day 26
Inside finishing coat and starting to fill the pool
with water!
Day 28
Pool is filled with water and almost ready to swim!
Day 29
We sneak in a swim and they start the roof and screen!
Day 30
2nd day working on the roof and screen.....
Day 31
3rd day on screen and roof.....& a little playtime!